This project covered the design, procurement, installation, testing and commissioning of three capacitor banks totalling 7.5 MVAR, for three medium-voltage substations within the Ar Razi plant.
The solution is built on ABB ABBACUS capacitor banks, selected to meet the plant’s technical and operational requirements. We also developed a new control system using National Instruments PLCs, increasing operational flexibility and allowing full integration into the substations’ SCADA systems.
Our scope ran from engineering and design through procurement and installation to full commissioning.