220 kV Substation for Lerești HPP

A refurbishment of the 20 kV substation at the 42 MW Lerești hydropower plant, plus a new 10 kV substation and a new SCADA system.

Client:

Hidroelectrica

Voltage Level:

220kV

Operating since:

2023

Location:

Lerești, Argeș County, Romania

Lerești HPP, a 42 MW hydropower plant on the Târgului river in central Romania, was refurbished by our team. We modernised the plant’s 20 kV substation and built a new 10 kV substation, complete with a new SCADA system.

Scope of work:

  • Installation, testing and commissioning
  • Basic and detailed engineering
  • MV switchgear procurement
  • SCADA and protection systems design
  • Protection relay configuration
  • FAT and SAT

See other projects

Helios PV Plant, 85.35 MWp

Helios PVPP is an 85.35 MWp / 72 MW photovoltaic power plant ...

Titu PV Plant, 54.23 MWp

We’ve delivered the Titu -54.23 MWp photovoltaic project in Dâmbovița County. As ...

Giurgiu PV Plant, 51.93 MWp

The Giurgiu Photovoltaic Power Plant was built on a former industrial ash ...

Teius PV Plant, 70MWp

With 68.99 MW of installed capacity, the Teiuș park uses tracking systems ...

Gogosu PV Plant, 42MWp

The Gogoșu photovoltaic project is a 41.94 MWp utility-scale solar installation delivered ...

Chisineu-Cris PV Plant, 54 MWp

The Chișineu-Criș Photovoltaic Power Plant (54.11 MWp) was completed and energised after ...

No more posts to show