Lerești HPP, a 42 MW hydropower plant on the Târgului river in central Romania, was refurbished by our team. We modernised the plant’s 20 kV substation and built a new 10 kV substation, complete with a new SCADA system.
Scope of work:
- Installation, testing and commissioning
- Basic and detailed engineering
- MV switchgear procurement
- SCADA and protection systems design
- Protection relay configuration
- FAT and SAT