Our Saudi Arabian team, ENEVO Arabia, carried out a comprehensive rehabilitation of the protection and control systems for the 230 kV GIS substation and the medium-voltage switchgear in MSS1.
The aim was to replace ageing infrastructure and lift the reliability and performance of the substation’s control systems — from relay replacement and panel upgrades through to system integration and commissioning.
The scope covered new LCC and protection panels, and the replacement of existing protection relays for the 34.5 kV MSS1, the 13.8 kV MSS1 and the 13.8 kV DR A/B/C feeders. A new SCADA system was deployed on SICAM PAS and SICAM SCC, and the substation was integrated with the main dispatch centre via SIEMENS SPECTRUM, giving centralised monitoring and coordination of the electrical network.
Design, installation, testing and commissioning of the protection, control and SCADA systems were all delivered in house.