OHTL 380kV – Brabo 3

Carried out between May 2024 and January 2025, this project covered the assembly and erection of 380 kV transmission poles as part of a complex high-voltage infrastructure programme in Belgium. The structures ranged from 65 to 132 metres in height and weighed between 67 and 386 tonnes each — a direct measure of the scale, […]

Doicești BESS, 15 MWh

Doicești BESS is a 15 MWh battery energy storage project developed for Silmaril, with 10.35 MW of installed AC power. Currently under delivery, the system will improve energy flexibility and operational efficiency on site, while adding a fast-responding resource that supports the reliability of the wider network.

Therme BESS, 0.8MWh

A 0.8 MWh battery energy storage system built around CATL cells was integrated into the Therme site to enable energy shifting, peak shaving and greater energy security for the facility. Working together with the on-site photovoltaic plant, storage increases the share of renewable energy consumed on site, reduces dependence on the grid and helps bring […]

Crucea Nord BESS, 72 MWh

Crucea Nord BESS is a 72 MWh battery energy storage project developed for Hidroelectrica, with 36 MW of installed AC power. Currently under delivery, the system is sized for grid balancing at scale: absorbing surplus generation, releasing it back at peak, and smoothing the intermittency that comes with a rising share of wind and solar […]

Tușnad BESS, 22.5MWh

Tușnad BESS is a 22.5 MWh battery energy storage project built for Silmaril, with 10.35 MW of installed AC power. Currently under delivery, the system will allow energy to be shifted across the day, respond quickly to grid signals and keep output stable — capabilities that grow more valuable as variable renewable capacity increases.