TSO Cybersecurity Assesment & Transformation Plan

A station-by-station security assessment of Romania’s main transmission substations, ending in a prioritised plan for closing the gaps it found.

Power:

MWp

Sector:

Power transmission

Scope:

Cybersecurity assessment and transformation plan

Coverage:

Main national grid substations

Status:

Delivered

Scope of work: a cybersecurity assessment and transformation plan for the main substations of the national grid.

Each substation was assessed individually, so that its current security posture could be understood and a transformation plan proposed against the specific findings and risks identified.

The assessment steps:

  • Asset identification — mapping every critical asset in the substation, including network devices, servers, control systems and data repositories
  • Network architecture review — segmentation, firewall configuration and access controls, verifying that critical systems are properly isolated and that the impact of any breach stays contained
  • Security policy review — checking existing policies, procedures and incident response plans for currency, completeness and alignment with industry best practice
  • Threat analysis — assessing threats and vulnerabilities specific to each substation, internal and external, including attack vectors such as unauthorised access, malware, social engineering and physical breach
  • Vulnerability scanning — automated scanning across all systems and networks to surface known vulnerabilities and prioritise remediation
  • Penetration testing — controlled, simulated attacks to expose weaknesses in the substation’s defences and measure how well existing controls actually hold

The findings were consolidated into a transformation plan for each station.

See other projects

Helios PV Plant, 85.35 MWp

Helios PVPP is an 85.35 MWp / 72 MW photovoltaic power plant ...

Titu PV Plant, 54.23 MWp

We’ve delivered the Titu -54.23 MWp photovoltaic project in Dâmbovița County. As ...

Giurgiu PV Plant, 51.93 MWp

The Giurgiu Photovoltaic Power Plant was built on a former industrial ash ...

Teius PV Plant, 70MWp

With 68.99 MW of installed capacity, the Teiuș park uses tracking systems ...

Gogosu PV Plant, 42MWp

The Gogoșu photovoltaic project is a 41.94 MWp utility-scale solar installation delivered ...

Chisineu-Cris PV Plant, 54 MWp

The Chișineu-Criș Photovoltaic Power Plant (54.11 MWp) was completed and energised after ...

No more posts to show